CorPower Ocean’s C4 Wave Energy Converter (WEC) has completed the first cycle of the ocean commissioning program at the Aguçadoura site in northern Portugal.
Since deployment in August 2023, all key aspects of the C4 system functions have now been successfully verified including power export to grid, automated control and monitoring of the system as well as safe Operations and Maintenance (O&M) methods.
The collected data allowed calibration of the digital twin, an extensive numerical model used to predict the system behaviour. Measured motion and power output data from the machine operating with novel ‘WaveSpring’ phase control has slightly exceeded predictions by the digital twin for the machinery settings used.
The first operational phase has been successfully concluded by disconnecting and towing the C4 device back to CorPower Ocean’s on-land base in Viana do Castelo for its first planned maintenance cycle. This demonstration of efficient O&M methods is a key goal of the C4 deployment program, to support scale-up to utility scale wave farms in the future.